Project information
Independent report on compliance with control and protection requirements and their performance during the electrical blackout of 28 April 2025
September 2025 - March 2026
Funding entity I-DE Redes Eléctricas Inteligentes, S.A.U
The objective of this project is to prepare an independent report on the performance of control and protection systems, and on their compliance with grid code requirements, during the moments preceding the nationwide power outage ("cero eléctrico") of 28 April 2025.
Research topics:
- Steady-state: Load flows, analysis of power system constraints, optimal load flows, voltage control ancilliary service,short-circuits, protections in transmission and ditribution networks
- Stability: Large disturbance stability, tuning of frequency loadshedding schemes, excitation control, small disturbance stability, tuning of power system stabilizers, identification of AVR and governor models
iDE_InformeApagon_2026